07/07/2025 Risk Management StandardUPDATE: More detail added into Section 3.3.4 in regards to the assigning of priority rankings and Hierarchy of Control to actions.
02/09/2025 Isolation of Plant and Equipment SpecificationUPDATE: Authorisation for isolation witness
16/09/2025 Safe Working at Height SpecificationUPDATE:
29/09/2025 Severe and Extreme Weather - Trigger Action Response Plan added sections as per below:
15/10/2025 Scaffolding SpecificationUPDATE: The change is around the length of time to which a scaffold must be inspected.
A Scaffold inspection must be completed a maximum of every twenty-eight (28) days from last inspection, or initial erection date.
Note, for scaffolds that are complex in design and subject to high loading (eg. during painting or blasting), or exposed to severe weather conditions (eg. cyclones or tidal impacts), reinspection intervals may be shortened.
This revised timeframe must be specified at handover by the constructor or WICET representative and clearly recorded on the scaffold tag and register.